Jannah Dam, Lebanon

  • 01/14/2019
  •  

After the successful completion of the cut-off wall works for seepage mitigation below the upstream and downstream cofferdams last year, we have mobilized recently our equipment for additional works consisting of the execution of a diaphragm wall bulkhead at the upstream side of the dam.

 

The Bauer cutter BC 40 is executing an up to 35 m deep diaphragm wall block, consisting of 3 rows of overlapping panels of 1.2 m thickness, with a total volume of approx. 4,600 m3.