Itteren Construction of Mixed-in-Place cut-off wall for a gravel mining depot along the river Maas. The cut-off wall was partly as a dike stabilisation wall. 

 

Main contractor:       Van den Biggelaar B.V.

 

Client:                        Consortium Grensmaas

 

Scope:                       14,000 m² Mixed-In-Place cut-off wall thickness 55 cm and depth approx. 10 m with a length of approx 1,500 m.

 

Execution period:    Jun. - Aug. 2008