The project is located in the Ashanti region, approx. 150 km west of Accra the capital of Ghana.
Bored secant pile wall for mine shaft. The embedment depth of the piles into the rock was between 0.5m and 1.5m
Geology:
Overburden consisting of sand and gravel
Bedrock
Scope of Works:
Miscellaneous:
Secant pile wall for the containment of the loose soil of the upper part of a 450m total deep shaft.
INFO
Construction Methods: Secant pile wall
Construction Materials: Concrete, steel
Main Equipment: BAUER BG 28
Construction period: December 2021